Chapter Ashburton Update

Stay informed with our latest construction updates.

4 April 2024
March Construction Update
  • Cladding complete
  • Plaster complete
  • Waterproofing complete
  • Tiling and joinery installation commenced.
  • Painting commenced.
85.6% completed
29 February 2024
February Construction Update
  • Full concrete structure including pre-cast panel installation complete.
  • Light Weight Steel installation on level 2 is complete.
  • Fire and Mechanical rough-in to the basement and ground floor are complete.
  • Installation of windows and balustrades complete.
  • Ground Floor and level 1 walls plastered. (level 1 ceilings 50%).
78.16% completed
19 February 2024
January Construction Update
  • Roof installed
  • Windows and Balustrades installed
  • Installation of mechanical exhaust and sprinkler droppers
  • Subhead and Subsill complete
68.6% completed
21 December 2023
December Construction Update
  • Level 2 lightweight steel installation completed.
  • Fire and mechanical service rough-in to the basement and ground floor commenced.
  • Subhead and subsill installation commenced.
  • Structure concrete pre-cast elements completed.
  • Preparation for roof installation commenced.
  • Strip out of 80% of all floors complete.
53.7% completed
29 November 2023
November Construction Update
  • Level 1 concrete slab pour 1 and 2 complete.
  • Level 2 concrete slab pour 1 and 2 complete.
  • The entire concrete structure was completed. This includes concrete and pre-cast elements.
  • Installation of hobs complete.
  • Lightweight steel installation to level 2 commenced.
47.48% completed
31 October 2023
October Update
  • Level 1 slab pour 1 and 2 complete.
  • Level 2 slab pour 1 complete.
  • Building Permit 3 received.
  • Pre-cast panel installation commenced.
43.9% completed
1 September 2023
September Update
25.51% completed
1 August 2023
August Construction Update
8.41% completed
1 July 2023
July Update
1 June 2023
June 2023
1 May 2023
May 2023